Hi,
We are upgrading SCM 5.0 with EHP2 SCM 7.0 and we are stuck in the execution phase. It is asking to run the report and complete the section C steps. When we click on Load Master data, its starting two job and the second job is failing with the below error.
Error: Job name: RESOURCE_LC_CLIENT_510.
LOGS:
Step 001 started (program /SAPAPO/RESOURCES_LC_CREATE, variant &
Prepare data
Create Resources
Create Resources with setup matrix
Wrap Up
Error creating resources in liveCache
Check the spool
Error occurred while creating resources in liveCache
Job cancelled after system exception ERROR_MESSAGE
Spool logs:
Resource Location Plng Versn ReturnCode Text
3400_RESOURCE 3400 000 48 Invalid time stream
DOP_BULK_RESOURCE 1750 000 48 Invalid time stream
DOP_DRUM_RESOURCE 1750 000 48 Invalid time stream
RES_1600 1600 000 48 Invalid time stream
RES_1100 1100 000 48 Invalid time stream
RES_1400 1400 000 48 Invalid time stream
TEMP1 1300 000 48 Invalid time stream
RES_1750 1750 000 48 Invalid time stream
DOP_2000_RES 2000 000 48 Invalid time stream
PC_2200_PACKAGING_1 2200 000 48 Invalid time stream
PC_2200_22003062_1 2200 000 48 Invalid time stream
Need your help, if some one face the same issue.
Thanks and Regards
Shaz Khan